| Project Milestone | Description (Days from Appointed Date) | Physical Progress (%) | Scheduled Date | Actual Achieved Date | Remarks |
|---|---|---|---|---|---|
| Milestone- I | 180 | 20% | 27-Feb-24 | 26-Mar-24 | |
| Milestone- II | 360 | 35% | 25-Aug-24 | 27-Aug-24 | |
| Milestone- III | 540 | 75% | 21-Feb-25 | 14-Oct-25 | |
| Scheduled Completion | 730 | 100% | 30-Aug-25 | 90% achieved till date remaining 10% is in progress. |