Project Milestone Schedule

Construction of 6-lane Greenfield Karnal Ring Road starting from NH- 44 near village Shamgarh (DesignKm0+000) and terminating at Karnal – Munak road (MDR-115) near village Samalakha (Design Km 34+500) Under Bharatmala Pariyojana in the state of Haryana on Hybrid Annuity Mode

Project Milestone Description (Days from Appointed Date) Physical Progress (%) Scheduled Date Actual Achieved Date Remarks
Milestone- I 180 20% 27-Feb-24 26-Mar-24
Milestone- II 360 35% 25-Aug-24 27-Aug-24
Milestone- III 540 75% 21-Feb-25 14-Oct-25
Scheduled Completion 730 100% 30-Aug-25 90% achieved till date remaining 10% is in progress.